Cracow Gold Mine

Tailings Dam Lift ‘TD1’

Tailings dam lift — decant pumps, HDPE pipe install and delivery pipe work.

Tailings Dam Lift ‘TD1’

Project detail

Client Cracow Gold Mine
Engineer SLR
Purpose Tailings lift ‘TD1’ — decant pumps, HDPE pipe install, delivery pipe work
Materials HDPE pipe DN200
Quantities 3km of pipe installed, welded and commissioned
Duration 6 weeks (completed 2015)