Cracow Gold Mine
Tailings Dam Lift ‘TD1’
Tailings dam lift — decant pumps, HDPE pipe install and delivery pipe work.
Project detail
| Client | Cracow Gold Mine |
|---|---|
| Engineer | SLR |
| Purpose | Tailings lift ‘TD1’ — decant pumps, HDPE pipe install, delivery pipe work |
| Materials | HDPE pipe DN200 |
| Quantities | 3km of pipe installed, welded and commissioned |
| Duration | 6 weeks (completed 2015) |